Project Start Date: Sat 12/30/06
Project Finish Date: Thu 1/4/07
Name | Duration | Start_Date | Finish_Date | Predecessors | Resource_Initials |
|---|---|---|---|---|---|
Tray Assembly | 1 day? | Sat 12/30/06 | Sat 12/30/06 | ||
Preparations | 2 days | Sat 12/30/06 | Sun 12/31/06 | ||
bathe aluminum (bottom, top, & cover assys and feet) | 2 days | Sat 12/30/06 | Sun 12/31/06 | ||
cut poly strips to length | 0.2 hrs | Sat 12/30/06 | Sat 12/30/06 | ||
revise MRPC pigtails and ohm-test | 2 hrs | Sat 12/30/06 | Sat 12/30/06 | ||
check size/tolerance of tray mechanical parts | 0.5 hrs | Sat 12/30/06 | Sat 12/30/06 | ||
Bottom Assy Prep Area | 1.13 days | Mon 1/1/07 | Tue 1/2/07 | ||
Bottom A Prep | 1.13 days | Mon 1/1/07 | Tue 1/2/07 | ||
select bottom assy | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 4 | A |
select feet and clean up rivet holes alignment | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 11 | A |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 12 | A |
clean feet w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 12 | A |
attach poly strips to feet | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 14,13 | A |
rivet feet to bottom assy | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 15 | A |
measure feet height & separations vs length | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 16 | A |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 17 | A |
seal rivets & corners w/ DC730 and return to rack | 0.4 hrs | Mon 1/1/07 | Mon 1/1/07 | 18 | A |
curing | 7.5 hrs | Mon 1/1/07 | Tue 1/2/07 | 19 | |
Bottom B Prep | 0.99 days | Mon 1/1/07 | Tue 1/2/07 | ||
select bottom assy | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 18 | A |
select feet and clean up rivet holes alignment | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 22 | A |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 23 | A |
clean feet w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 23 | A |
attach poly strips to feet | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 24,25 | A |
rivet feet to bottom assy | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 26 | A |
measure feet height & separations vs length | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 27 | A |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 28 | A |
seal rivets & corners w/ DC730 and return to rack | 0.4 hrs | Mon 1/1/07 | Mon 1/1/07 | 29 | A |
curing | 6.4 hrs | Mon 1/1/07 | Tue 1/2/07 | 30 | |
Bottom C Prep | 0.85 days | Mon 1/1/07 | Tue 1/2/07 | ||
select bottom assy | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 29 | A |
select feet and clean up rivet holes alignment | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 33 | A |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 34 | A |
clean feet w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 34 | A |
attach poly strips to feet | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 35,36 | A |
rivet feet to bottom assy | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 37 | A |
measure feet height & separations vs length | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 38 | A |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 39 | A |
seal rivets & corners w/ DC730 and return to rack | 0.4 hrs | Mon 1/1/07 | Mon 1/1/07 | 40 | A |
curing | 5.3 hrs | Mon 1/1/07 | Tue 1/2/07 | 41 | |
Top Assy Prep Area | 1.13 days | Mon 1/1/07 | Tue 1/2/07 | ||
Top A Prep | 1.13 days | Mon 1/1/07 | Tue 1/2/07 | ||
Clean interior with IPA | 0.05 hrs | Mon 1/1/07 | Mon 1/1/07 | 4 | B,C |
seal pem studs | 0.5 hrs | Mon 1/1/07 | Mon 1/1/07 | 46 | B |
clean F/T end w/ IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 47 | B |
install HV and gas bulkhead connectors | 0.3 hrs | Mon 1/1/07 | Mon 1/1/07 | 48 | B |
invert and clean near pem studs with IPA | 0.05 hrs | Mon 1/1/07 | Mon 1/1/07 | 49 | B,C |
select 8 TINOs and document | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 50 | B |
install 8 TINOs | 1 hr | Mon 1/1/07 | Mon 1/1/07 | 51 | B,C |
curing | 6.9 hrs | Mon 1/1/07 | Tue 1/2/07 | 52 | |
Top B Prep | 0.86 days | Mon 1/1/07 | Tue 1/2/07 | ||
Clean interior with IPA | 0.05 hrs | Mon 1/1/07 | Mon 1/1/07 | 52 | B,C |
seal pem studs | 0.5 hrs | Mon 1/1/07 | Mon 1/1/07 | 55 | B |
clean F/T end w/ IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 56 | B |
install HV and gas bulkhead connectors | 0.3 hrs | Mon 1/1/07 | Mon 1/1/07 | 57 | B |
invert and clean near pem studs with IPA | 0.05 hrs | Mon 1/1/07 | Mon 1/1/07 | 58 | B,C |
select 8 TINOs and document | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 59 | B |
install 8 TINOs | 1 hr | Mon 1/1/07 | Mon 1/1/07 | 60 | B,C |
curing | 4.8 hrs | Mon 1/1/07 | Tue 1/2/07 | 61 | |
Top C Prep | 0.6 days | Mon 1/1/07 | Tue 1/2/07 | ||
Clean interior with IPA | 0.05 hrs | Mon 1/1/07 | Mon 1/1/07 | 61 | B,C |
seal pem studs | 0.5 hrs | Mon 1/1/07 | Mon 1/1/07 | 64 | B |
clean F/T end w/ IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 65 | B |
install HV and gas bulkhead connectors | 0.3 hrs | Mon 1/1/07 | Mon 1/1/07 | 66 | B |
invert and clean near pem studs with IPA | 0.05 hrs | Mon 1/1/07 | Mon 1/1/07 | 67 | B,C |
select 8 TINOs and document | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 68 | B |
install 8 TINOs | 1 hr | Mon 1/1/07 | Mon 1/1/07 | 69 | B,C |
curing | 2.7 hrs | Mon 1/1/07 | Tue 1/2/07 | 70 | |
Pivot Table | 0.83 days | Tue 1/2/07 | Tue 1/2/07 | ||
Top A Fill | 0.28 days | Tue 1/2/07 | Tue 1/2/07 | ||
Select Top, attach upper brackets and cover assy | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 53 | A,B |
invert and install lower brackets | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 75 | A,B |
install "lower" inner side | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 76 | A,B |
pivot and install MRPCs | 1.5 hrs | Tue 1/2/07 | Tue 1/2/07 | 77 | A,B |
install "upper" inner side | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 78 | A,B |
pivot and install bottom assy | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 79 | A,B |
move to flat table | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 80 | A,B |
Top B Fill | 0.28 days | Tue 1/2/07 | Tue 1/2/07 | ||
Select Top, attach upper brackets and cover assy | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 62,81 | A,B |
invert and install lower brackets | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 83 | A,B |
install "lower" inner side | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 84 | A,B |
pivot and install MRPCs | 1.5 hrs | Tue 1/2/07 | Tue 1/2/07 | 85 | A,B |
install "upper" inner side | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 86 | A,B |
pivot and install bottom assy | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 87 | A,B |
move to flat table | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 88 | A,B |
Top C Fill | 0.28 days | Tue 1/2/07 | Tue 1/2/07 | ||
Select Top, attach upper brackets and cover assy | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 71,89 | A,B |
invert and install lower brackets | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 91 | A,B |
install "lower" inner side | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 92 | A,B |
pivot and install MRPCs | 1.5 hrs | Tue 1/2/07 | Tue 1/2/07 | 93 | A,B |
install "upper" inner side | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 94 | A,B |
pivot and install bottom assy | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 95 | A,B |
move to flat table | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 96 | A,B |
Tray Interiors | 1.73 days? | Tue 1/2/07 | Thu 1/4/07 | ||
Tray A Interior | 0.4 days | Tue 1/2/07 | Tue 1/2/07 | ||
remove bottom assy | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 81 | A,B |
install gas tubing | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 101 | A,B |
install and test HV bus | 3 hrs | Tue 1/2/07 | Tue 1/2/07 | 102 | C |
Tray B Interior | 0.75 days | Tue 1/2/07 | Wed 1/3/07 | ||
remove bottom assy | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 102 | A,B |
install gas tubing | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 105 | A,B |
install and test HV bus | 3 hrs | Tue 1/2/07 | Wed 1/3/07 | 106,103 | C |
Tray C Interior | 1.1 days | Tue 1/2/07 | Wed 1/3/07 | ||
remove bottom assy | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 106 | A,B |
install gas tubing | 0.1 hrs | Tue 1/2/07 | Tue 1/2/07 | 109 | A,B |
install and test HV bus | 3 hrs | Wed 1/3/07 | Wed 1/3/07 | 110,107 | C |
Tray A HV Test | 0.5 hrs | Tue 1/2/07 | Tue 1/2/07 | 103 | A |
Tray B HV Test | 0.5 hrs | Wed 1/3/07 | Wed 1/3/07 | 107 | A |
Tray C HV Test | 0.5 hrs | Wed 1/3/07 | Wed 1/3/07 | 111 | A |
Tray A Final Seal | 1.26 days | Tue 1/2/07 | Thu 1/4/07 | ||
final seal | 0.5 hrs | Tue 1/2/07 | Tue 1/2/07 | 113 | A,B |
curing | 1.2 days | Tue 1/2/07 | Thu 1/4/07 | 118 | |
Tray B Final Seal | 0.89 days? | Wed 1/3/07 | Thu 1/4/07 | ||
final seal | 0.5 hrs | Wed 1/3/07 | Wed 1/3/07 | 114 | A,B |
curing | 0.83 days? | Wed 1/3/07 | Thu 1/4/07 | 121 | |
Tray C Final Seal | 0.51 days? | Wed 1/3/07 | Thu 1/4/07 | ||
final seal | 0.5 hrs | Wed 1/3/07 | Wed 1/3/07 | 115 | A,B |
curing | 0.45 days? | Wed 1/3/07 | Thu 1/4/07 | 124 |