Project Start Date: Mon 1/1/07
Project Finish Date: Sat 1/6/07
Name | Duration | Start_Date | Finish_Date | Predecessors |
|---|---|---|---|---|
Tray Assembly | 1 day? | Mon 1/1/07 | Mon 1/1/07 | |
Preparations | 0 days | Mon 1/1/07 | Mon 1/1/07 | |
bathe aluminum (bottom, top, & cover assys and feet) | 0 days | Mon 1/1/07 | Mon 1/1/07 | |
cut poly strips to length | 0 hrs | Mon 1/1/07 | Mon 1/1/07 | |
revise MRPC pigtails and ohm-test | 0 hrs | Mon 1/1/07 | Mon 1/1/07 | |
check size/tolerance of tray mechanical parts | 0 hrs | Mon 1/1/07 | Mon 1/1/07 | |
mechanical parts ready | 0 days | Mon 1/1/07 | Mon 1/1/07 | 4,5,6,7 |
Bottom Assy Prep Area | 1.23 days | Mon 1/1/07 | Tue 1/2/07 | |
Bottom A Prep | 1.13 days | Mon 1/1/07 | Tue 1/2/07 | |
select bottom assy | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 8 |
select feet and clean up rivet holes alignment | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 12 |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 13 |
clean feet w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 13 |
attach poly strips to feet | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 15,14 |
rivet feet to bottom assy | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 16 |
measure feet height & separations vs length | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 17 |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 18 |
seal rivets & corners w/ DC730 and return to rack | 0.4 hrs | Mon 1/1/07 | Mon 1/1/07 | 19 |
curing | 7.5 hrs | Mon 1/1/07 | Tue 1/2/07 | 20 |
Bottom B Prep | 0.99 days | Mon 1/1/07 | Tue 1/2/07 | |
select bottom assy | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 20 |
select feet and clean up rivet holes alignment | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 23 |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 24 |
clean feet w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 24 |
attach poly strips to feet | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 25,26 |
rivet feet to bottom assy | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 27 |
measure feet height & separations vs length | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 28 |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 29 |
seal rivets & corners w/ DC730 and return to rack | 0.4 hrs | Mon 1/1/07 | Mon 1/1/07 | 30 |
curing | 6.4 hrs | Mon 1/1/07 | Tue 1/2/07 | 31 |
Bottom C Prep | 0.85 days | Mon 1/1/07 | Tue 1/2/07 | |
select bottom assy | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 31 |
select feet and clean up rivet holes alignment | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 34 |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 35 |
clean feet w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 35 |
attach poly strips to feet | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 36,37 |
rivet feet to bottom assy | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 38 |
measure feet height & separations vs length | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 39 |
clean bottom assy interior near rivet holes w/ IPA | 0.2 hrs | Mon 1/1/07 | Mon 1/1/07 | 40 |
seal rivets & corners w/ DC730 and return to rack | 0.4 hrs | Mon 1/1/07 | Mon 1/1/07 | 41 |
curing | 5.3 hrs | Mon 1/1/07 | Tue 1/2/07 | 42 |
Top Assy Prep Area | 1.16 days | Mon 1/1/07 | Tue 1/2/07 | |
Top A Prep | 1 day | Mon 1/1/07 | Mon 1/1/07 | |
Clean interior with IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 4 |
seal pem studs | 0.5 hrs | Mon 1/1/07 | Mon 1/1/07 | 47 |
clean F/T end w/ IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 48 |
install HV and gas bulkhead connectors | 0.3 hrs | Mon 1/1/07 | Mon 1/1/07 | 49 |
invert and clean near pem studs with IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 50 |
select 8 TINOs and document | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 51 |
install 8 TINOs | 1 hr | Mon 1/1/07 | Mon 1/1/07 | 52 |
curing | 5.8 hrs | Mon 1/1/07 | Mon 1/1/07 | 53 |
Top B Prep | 0.6 days | Mon 1/1/07 | Mon 1/1/07 | |
Clean interior with IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 53 |
seal pem studs | 0.5 hrs | Mon 1/1/07 | Mon 1/1/07 | 56 |
clean F/T end w/ IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 57 |
install HV and gas bulkhead connectors | 0.3 hrs | Mon 1/1/07 | Mon 1/1/07 | 58 |
invert and clean near pem studs with IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 59 |
select 8 TINOs and document | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 60 |
install 8 TINOs | 1 hr | Mon 1/1/07 | Mon 1/1/07 | 61 |
curing | 2.6 hrs | Mon 1/1/07 | Mon 1/1/07 | 62 |
Top C Prep | 0.61 days | Mon 1/1/07 | Tue 1/2/07 | |
Clean interior with IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 62 |
seal pem studs | 0.5 hrs | Mon 1/1/07 | Mon 1/1/07 | 65 |
clean F/T end w/ IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 66 |
install HV and gas bulkhead connectors | 0.3 hrs | Mon 1/1/07 | Mon 1/1/07 | 67 |
invert and clean near pem studs with IPA | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 68 |
select 8 TINOs and document | 0.1 hrs | Mon 1/1/07 | Mon 1/1/07 | 69 |
install 8 TINOs | 1 hr | Mon 1/1/07 | Mon 1/1/07 | 70 |
curing | 2.7 hrs | Mon 1/1/07 | Tue 1/2/07 | 71 |
Pivot Table | 1.28 days | Tue 1/2/07 | Wed 1/3/07 | |
Top A Fill | 0.43 days | Tue 1/2/07 | Tue 1/2/07 | |
Select Top, attach upper brackets and cover assy | 0.4 hrs | Tue 1/2/07 | Tue 1/2/07 | 54 |
invert and install lower brackets | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 76 |
install "lower" inner side | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 77 |
pivot and install MRPCs | 2 hrs | Tue 1/2/07 | Tue 1/2/07 | 78 |
install "upper" inner side | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 79 |
pivot and install bottom assy | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 80,21 |
move to flat table | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 81 |
Top B Fill | 0.43 days | Tue 1/2/07 | Tue 1/2/07 | |
Select Top, attach upper brackets and cover assy | 0.4 hrs | Tue 1/2/07 | Tue 1/2/07 | 63,82 |
invert and install lower brackets | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 84 |
install "lower" inner side | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 85 |
pivot and install MRPCs | 2 hrs | Tue 1/2/07 | Tue 1/2/07 | 86 |
install "upper" inner side | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 87 |
pivot and install bottom assy | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 88,32 |
move to flat table | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 89 |
Top C Fill | 0.43 days | Tue 1/2/07 | Wed 1/3/07 | |
Select Top, attach upper brackets and cover assy | 0.4 hrs | Tue 1/2/07 | Tue 1/2/07 | 72,90 |
invert and install lower brackets | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 92 |
install "lower" inner side | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 93 |
pivot and install MRPCs | 2 hrs | Tue 1/2/07 | Wed 1/3/07 | 94 |
install "upper" inner side | 0.2 hrs | Wed 1/3/07 | Wed 1/3/07 | 95 |
pivot and install bottom assy | 0.2 hrs | Wed 1/3/07 | Wed 1/3/07 | 96,43 |
move to flat table | 0.2 hrs | Wed 1/3/07 | Wed 1/3/07 | 97 |
Tray Interiors | 1.59 days? | Tue 1/2/07 | Thu 1/4/07 | |
Tray A Interior | 0.43 days | Tue 1/2/07 | Tue 1/2/07 | |
remove bottom assy | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 82 |
install gas tubing | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 102 |
install and test HV bus | 3 hrs | Tue 1/2/07 | Tue 1/2/07 | 103 |
Tray B Interior | 0.43 days | Tue 1/2/07 | Wed 1/3/07 | |
remove bottom assy | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 90,104 |
install gas tubing | 0.2 hrs | Tue 1/2/07 | Tue 1/2/07 | 106 |
install and test HV bus | 3 hrs | Tue 1/2/07 | Wed 1/3/07 | 107,104 |
Tray C Interior | 0.43 days | Wed 1/3/07 | Wed 1/3/07 | |
remove bottom assy | 0.2 hrs | Wed 1/3/07 | Wed 1/3/07 | 98,108 |
install gas tubing | 0.2 hrs | Wed 1/3/07 | Wed 1/3/07 | 110 |
install and test HV bus | 3 hrs | Wed 1/3/07 | Wed 1/3/07 | 111,108 |
Tray A HV Test | 0.5 hrs | Tue 1/2/07 | Tue 1/2/07 | 104 |
Tray B HV Test | 0.5 hrs | Wed 1/3/07 | Wed 1/3/07 | 108 |
Tray C HV Test | 0.5 hrs | Wed 1/3/07 | Wed 1/3/07 | 112 |
Tray A Final Seal | 1.09 days | Tue 1/2/07 | Thu 1/4/07 | |
final seal | 0.5 hrs | Tue 1/2/07 | Tue 1/2/07 | 114 |
curing | 1.03 days | Tue 1/2/07 | Thu 1/4/07 | 119 |
Tray B Final Seal | 0.67 days | Wed 1/3/07 | Thu 1/4/07 | |
final seal | 0.5 hrs | Wed 1/3/07 | Wed 1/3/07 | 115 |
curing | 0.61 days | Wed 1/3/07 | Thu 1/4/07 | 122 |
Tray C Final Seal | 0.24 days? | Wed 1/3/07 | Thu 1/4/07 | |
final seal | 0.5 hrs | Wed 1/3/07 | Wed 1/3/07 | 116 |
curing | 0.18 days? | Wed 1/3/07 | Thu 1/4/07 | 125 |
Tray A Superstructure | 0.18 days | Thu 1/4/07 | Thu 1/4/07 | 120 |
invert and remove cover assy | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 120 |
install shim layer | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 129 |
install cooling loop | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 130 |
install LV bus | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 131 |
install TDIG layer | 1 hr | Thu 1/4/07 | Thu 1/4/07 | 132 |
Tray B Superstructure | 0.18 days | Thu 1/4/07 | Thu 1/4/07 | 123 |
invert and remove cover assy | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 123 |
install shim layer | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 135 |
install cooling loop | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 136 |
install LV bus | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 137 |
install TDIG layer | 1 hr | Thu 1/4/07 | Thu 1/4/07 | 138 |
Tray C Superstructure | 0.18 days | Thu 1/4/07 | Thu 1/4/07 | 126 |
invert and remove cover assy | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 126 |
install shim layer | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 141 |
install cooling loop | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 142 |
install LV bus | 0.1 hrs | Thu 1/4/07 | Thu 1/4/07 | 143 |
install TDIG layer | 1 hr | Thu 1/4/07 | Thu 1/4/07 | 144 |
Prepare Parts for Next Week | 1.86 days? | Thu 1/4/07 | Sat 1/6/07 | 145 |